Design & installation Guide For McQuay MDS Multi System
4.3.7 Process sequence of air leakage test
Main points of testing
Please test as follows:
The Pressure charging must be tested both in liquid pipe and gas pipe.
First step, keep 3.0kg/cm2 pressure gas for more than 3 minutes---may be can find big gap;
Second step, keep 15.0kg/cm2 pressure gas for more than 3 minutes---may be can
find big gap;
Third step, keep 28.0kg/cm2 pressure gas for more than 24 hours.
Notes:
Keep the 28.0kg/cm2 pressure gas must more than 24 hours.
The pressure can not be more than 28.0kg/cm2!
Check the pressure decrease or not
If the pressure remain the same, then it is OK;
If the pressure decrease, then we should find out the leak gap.
If the ambient temperature when pressure is charged is different from the temperature when
observing, the pressure need to be modified as follows:
Modified value = (temperature when pressure is charged- temperature when observing)x 0.1;
e.g.: when pressure is charged to 28.0kg/cm2 and the ambient temperature is 25; after
24 hours, the pressure is 27.5kg/cm2 and the temperature is 20, then you can
have a conclusion that it is OK.
No
yes
Pressure
charging
Pass
check and
maintain it
refrigerant piping
assembly finished
is the pressure
released?